To illustrate what I was talking about last night (trucks waiting for extended periods from BS to WS), here's the data from today's stickered RHOs.
There are 24 trucks. 5 of them were stickered in 1 day, 3 were stickered in 2 days, etc.
As you can see, more than half of them waited 23 days or longer (up to 40 days).
EDIT: And those last two (showing 40 days) are probably longer than that, as I only started looking for build sheets on 10/24, so that's the date I have recorded. Those two could have been built in early October or even August-September.
View attachment 21873